FPL is beginning the first phase of their Storm Secure Underground project in Lighthouse Point beginning Wednesday, April 22, 2020. There will be directional drilling and other activities occurring in the area utilizing trucks and machinery resulting in occasional lane closures.
• Marina Area: Project complete
• NE 21 Way between Sample Road and NE 38 St: Project substantially complete; final elements to be addressed
• NE 36 Ct/NE 37 St/NE 37 Ct from NE 22 Terr to NE 23 Ave: Project substantially complete; final elements to be addressed
• NE 26 Ave from NE 39 St south to cul-de-sac: Project substantially complete; final elements to be addressed
• NE 24 Ave from NE 39 St south to cul-de-sac: Project substantially complete; final elements to be addressed
• NE 33 ST/NE 34 St from NE 28 Ave to NE 29 Ave: Project substantially complete; final elements to be addressed
New Permitted Areas

All projects with start dates in February and March are underway. Final elements include overhead wire removal, transformer removal, pole topping where permitted and sod restoration.
Primary Project Contacts
FPL: Austin Ragoonanan
Email Austin Ragoonanan
Telephone: 754-209-5933
FPL:Corey Erstad
Email Corey Erstad
Telephone: 786-682-5780